Skip to main content

No, Indian Point Unit 2's License Has Not Expired

Allow us a moment to clarify.
Over the past few weeks we've seen a lot of chatter over Indian Point Unit 2 as it enters an NRC-approved period of extended operation (PEO) beginning on September 28.

On Twitter, we're seeing a lot of statements like this one from Elizabeth Douglas of Inside Climate News. The tweet inspired NEI media manager Tom Kauffman to send Douglas the following email:
Dear Ms. Douglass,

Indian Point Unit 2’s license has not expired.

Because Entergy Corp. filed timely and comprehensive license renewal applications for both Indian Point Units 2 and 3 in April 2007, more than five years ahead of IP2’s original expiration date of Sept. 28, 2013, and more than seven years ahead of IP3’s original expiration date of Dec. 12, 2015. The early applications satisfy the requirements of the Timely Renewal Doctrine, a well-established federal law that extends the current operating license until the license renewal process is complete.

The Timely Renewal Doctrine is law under the federal Administrative Procedures Act that is generally applicable to regulatory and administrative federal agencies including the Nuclear Regulatory Commission, and is available to all nuclear energy facilities that apply for a 20-year license renewal at least five years before the expiration of their current license. Indian Point 2 will become the first nuclear energy facility to operate with a license extended by Timely Renewal Doctrine because of the unprecedented number of challenges to its license renewal application that must be addressed by the NRC.

Indian Point 2 will enter the period of timely renewal on September 28, 2013 and has met all of the federal requirements under the Timely Renewal Doctrine. The continued operation of Indian Point 2 under the Timely Renewal Doctrine in no way reduces the level of safety of the facility. Indian Point 2 currently meets all federal regulatory requirements, will continue to be thoroughly inspected, and must continue to adhere to all regulatory requirements. Both operating units at Indian Point are very safe and have earned the Nuclear Regulatory Commission's highest safety ratings over the past nine years and have maintained operational reliability higher than the nuclear industry’s national average. And Indian Point’s owner, Entergy Corp., has invested more than $1 billion to upgrade and enhance both operating facilities for continued safe operation.

If you have any questions, please feel free to contact me.

Best,
Tom Kauffman
For more on the work being done at Indian Point during the period of extended operations, see the Indian Point website. Here at NEI, our news team has been covering the story for several weeks, including a story detailing the $1 billion in upgrades the plant has implemented over the past decade to help make it one of the most efficient in the nation.

Comments

Joffan said…
And why isn't the NRC directly rebutting this public nonsense?

In any case, the ridiculously drawn-out process of license renewal for Indian Point is in itself an indication that the NRC is simply not doing its job, certainly on a strategic level. It has become - whether through intent or spinelessness in the face of frivolous intervention - an expensive blocking mechanism for nuclear power.
Anonymous said…
What are you worried about? How is the agency "blocking" nuclear power in this process? NRC has NEVER denied a power reactor license renewal request. Not once.
Anonymous said…
Anonymous, you imply that the NRC is a spineless rubber-stamping machine, in bed with the nuclear industry. False, false, false.

Years of massive paperwork and evaluation are involved, License extensions are only issued when the plant is seen to have complied with all the required refurbishments.

Anonymous said…
You're putting words in my mouth. All I said is NRC has never denied a renewal request, so I don't understand how those reviews are functioning as "an expensive blocking mechanism for nuclear power."

They can continue to operate during completion of the renewal reviews if the application was filed on a timely basis, and ultimately the application will be approved. Where's the "blocking"?
Joffan said…
@Anonymous1: NRC does indeed put expensive blocks in the way of nuclear. The surmounting of those blocks is not free, not easy and not quick. Your apparent ignorance of the money value of time is either disingenuous or disqualifies you from serious debate on these issues.
Anonymous said…
@ Joffan --

Perhaps if you browsed online a little more extensively you'd realize the NRC was way ahead of you:

http://public-blog.nrc-gateway.gov/2013/08/20/indian-points-timely-renewal-the-background/

You say "blocks," people who understand the process say "reasonable review requirements" that utilities have understood for more than a decade when applying for a renewed license.

Indian Point keeps on running during the review, so what was your point again?

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should