Skip to main content

First Concrete Pour of Westinghouse's AP1000 Completed at China's Sanmen Nuclear Site

From Westinghouse:
Westinghouse Electric Company, its consortium partner The Shaw Group Inc., China's State Nuclear Power Technology Corporation (SNPTC) and Sanmen Nuclear Power Company of China National Nuclear Corporation today announced the successful completion, on schedule, of the first pour of basemat structural concrete for the nuclear island at Sanmen, the site of the first of four Westinghouse AP1000™ nuclear power plants to be built under a contract signed in 2007.
AP1000 Sanmen Nuclear Plant
...

"Completion of concrete pour is a major milestone that visibly moves the Sanmen project from the design and discussion stage to the construction stage," he said. "More importantly, by getting this project underway on schedule, we are further helping to ensure that baseload electricity generation will begin at this plant as intended in 2013."

...

The pour encompassed 5,200 cubic meters of concrete, 950 tons of reinforcing steel and 1000 anchor bolts. The concrete will serve as the foundation for all of the nuclear island buildings, including the containment vessel and the shield building.
Best of luck!

Comments

theanphibian said…
Where did you get the pictures from? Can we get them with a free license?
Anonymous said…
Westinghouse is clearly out in the lead now, ahead of Areva and GEH in showing what the best vendor practice should be. Great job!
Todays energy demand can overtake by nuclear energy only, you can seen better picture from INDIA.
David Bradish said…
Where did you get the pictures from?The first picture was from SNPTC's press release of the pour and the second one came from China's Xinhua News Agency.
gunter said…
Granted you can pour a lot of concrete under a socialized energy policy.

Wonder how the QA/QC is in China?

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...

Nuclear Utility Moves Up in Credit Ratings, Bank is "Comfortable with Nuclear Strategy"

Some positive signs that nuclear utilities can continue to receive positive ratings even while they finance new nuclear plants for the first time in decades: Wells Fargo upgrades SCANA to Outperform from Market Perform Wells analyst says, "YTD, SCG shares have underperformed the Regulated Electrics (total return +2% vs. +9%). Shares trade at 11.3X our 10E EPS, a modest discount to the peer group median of 11.8X. We view the valuation as attractive given a comparatively constructive regulatory environment and potential for above-average long-term EPS growth prospects ... Comfortable with Nuclear Strategy. SCG plans to participate in the development of two regulated nuclear units at a cost of $6.3B, raising legitimate concerns regarding financing and construction. We have carefully considered the risks and are comfortable with SCG’s strategy based on a highly constructive political & regulatory environment, manageable financing needs stretched out over 10 years, strong partners...