MSNBC Story on the Economics of New Nuclear Build

After four days of looking at the nuclear energy industry through the prism of Washington lobbying, MSNBC's last piece of reporting on the nuclear energy industry turns to the challenge of financing new nuclear build. It's easily the best piece in the entire series:
The economics of building nuclear power plants began to short-circuit in the 1970s, after a building boom that lasted more than a decade. Part of the problem was the widespread use of so-called “cost-plus” contracts, in which the companies building plants were not held to a fixed price, according to Dan Keuter, head of nuclear business development for Entergy, which has applied for a site permit to build a new nuclear unit.

“You had multiple subcontractors working on cost plus basis,” he said. “So they were actually motivated not to get it done early. ... And (they) were definitely not motivated to do it within budget because the more they spent, the more they got.

Most plants were designed one at a time from the ground up; in some cases, engineers and designers were still working on plans as construction was under way, said Keuter. Changing regulatory requirements created further delays.

As a result, construction schedules began to double and triple, costs skyrocketed and projects in the pipeline were canceled. For those projects that continued, rising carrying costs as interest rates hit double-digits added to already huge cost overruns. By the end of the decade, the nuclear power industry was buried under a pile of debt.
All very true, though MSNBC's John Schoen does a very good job of updating just what's changed since the last major build cycle in the U.S. For more hard data on finanical issues in the nuclear energy industry, visit NEI's Financial Center on our Web site. And again, I suggest anyone wanting to examine the challenges facing the industry to review the presentation our CEO Skip Bowman gave to the National Academy of Engineering last Fall.

Technorati tags: , , , , , , ,

Comments

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...

Nuclear Utility Moves Up in Credit Ratings, Bank is "Comfortable with Nuclear Strategy"

Some positive signs that nuclear utilities can continue to receive positive ratings even while they finance new nuclear plants for the first time in decades: Wells Fargo upgrades SCANA to Outperform from Market Perform Wells analyst says, "YTD, SCG shares have underperformed the Regulated Electrics (total return +2% vs. +9%). Shares trade at 11.3X our 10E EPS, a modest discount to the peer group median of 11.8X. We view the valuation as attractive given a comparatively constructive regulatory environment and potential for above-average long-term EPS growth prospects ... Comfortable with Nuclear Strategy. SCG plans to participate in the development of two regulated nuclear units at a cost of $6.3B, raising legitimate concerns regarding financing and construction. We have carefully considered the risks and are comfortable with SCG’s strategy based on a highly constructive political & regulatory environment, manageable financing needs stretched out over 10 years, strong partners...