NRC’s 90 Day Report from the Fukushima Task Force

image Today, the Nuclear Regulatory Commission published its Fukushima task force’s Recommendations for Enhancing Reactor Safety in the 21st Century (pdf). This is a significant report because it sets the stage for what’s to come over the next few years to enhance nuclear safety. Here are a few nuggets from our press release on the report:

The task force report confirms the safety of U.S. nuclear energy facilities and recommends actions to enhance U.S. nuclear plant readiness to safely manage severe events.

…

The task force report does not cite significant data from the Fukushima accident to support many of its recommendations. Given the mammoth challenge it faced in gathering and evaluating the still-incomplete information from Japan, the agency should seek broader engagement with stakeholders on the task force report to ensure that its decisions are informed by the best information possible.

…

The industry reiterates our commitment to make nuclear plant safety our top priority. Even as the NRC and industry separately have taken steps to identify additional layers of protection to enhance nuclear plant safety, the NRC and many of our nation’s leaders have recognized that U.S. reactors are safe.

Besides what NEI has to say, here are a few nuggets from the NRC report to mention:

The current regulatory approach, and more importantly, the resultant plant capabilities allow the Task Force to conclude that a sequence of events like the Fukushima accident is unlikely to occur in the United States and some appropriate mitigation measures have been implemented, reducing the likelihood of core damage and radiological releases. Therefore, continued operation and continued licensing activities do not pose an imminent risk to public health and safety. p. vii

…

The primary responsibility for safety rests with the licensees, and the NRC holds licensees accountable for meeting regulatory requirements. p. 19

…

This [proposed] framework, by itself, would not create requirements nor eliminate any current requirements. It would provide a more coherent structure within the regulations to facilitate Commission decisions relating to what issues should be subject to NRC requirements and what those requirements ought to be. p. 21

…

As discussed earlier, the Task Force believes the voluntary industry initiatives could play a useful and valuable role in the suggested framework. p. 21

…

In a new regulatory framework, risk assessment and defense-in-depth would be combined more formally. p. 21

And here’s a valuable nugget on new plant designs:

By nature of their passive designs and inherent 72-hour coping capability for core, containment, and spent fuel pool cooling with no operator action required, the ESBWR and AP1000 designs have many of the design features and attributes necessary to address the Task Force recommendations. The Task Force supports completing those design certification rulemaking activities without delay. p. 71

Good to hear. For more on the industry’s perspective, see our Chief Nuclear Officer, Tony Pietrangelo, in an interview with Reuters Insider.

Comments

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...

Nuclear Utility Moves Up in Credit Ratings, Bank is "Comfortable with Nuclear Strategy"

Some positive signs that nuclear utilities can continue to receive positive ratings even while they finance new nuclear plants for the first time in decades: Wells Fargo upgrades SCANA to Outperform from Market Perform Wells analyst says, "YTD, SCG shares have underperformed the Regulated Electrics (total return +2% vs. +9%). Shares trade at 11.3X our 10E EPS, a modest discount to the peer group median of 11.8X. We view the valuation as attractive given a comparatively constructive regulatory environment and potential for above-average long-term EPS growth prospects ... Comfortable with Nuclear Strategy. SCG plans to participate in the development of two regulated nuclear units at a cost of $6.3B, raising legitimate concerns regarding financing and construction. We have carefully considered the risks and are comfortable with SCG’s strategy based on a highly constructive political & regulatory environment, manageable financing needs stretched out over 10 years, strong partners...