Skip to main content

Brown's Ferry Re-Start on Schedule for May 2007

That's the word from our friends at the TVA. This project is very important to the American nuclear industry, and I'm proud of the work TVA has completed thus far. Keep it up, I'm looking forward to next May.

Click here for more on the TVA's nuclear program.

Technorati tags: , , , ,

Comments

Original_Jeff said…
The NRC's quaterly public meeting with the TVA Browns Ferry Unit 1 Restart Project Management was on Thursday. Here are a few notes I took (I am not an engineer, so sorry for mistakes!):
- The nuclear fuel arrived on site on July 17 from GE.
- Expecting a December 2006 fuel load.
- Power generation is on schedule for May 2007. There was some hinting that this might happen earlier.
- The $1.8 billion restart project is on budget.
- Browns Ferry staffing was at 898 persons prior to restart. They are at 1015 now. They forecast a need for 1047 staff members to support 3-unit operation.
- About 2,300 contractor employees on site.
- Stone & Webster is the prime construction contractor.
- Bechtel is the prime design contractor.
- NRC will have an additional permanent on site inspector (2 -> 3), since it is their custom to have the same number of resident inspectors as operating units.
- There is a tremendous amount of testing and inspection, and internal and external approvals required as each of the many subsystems are turned over to the plant operators. (The subsystems of the Unit 1 are "owned" by the restart project, and the restart project sort of has to "prove" that the subsystems are appropriately designed and constructed and inspected/tested before the "operating plant" will accept them for operation.)
- The project involved 605,529 feet of cabling, of which 83% is installed.
- There are 41,038 cable terminations, of which 89% are complete.
- There is 15,137 feet of small bore piping, of which 96% are complete.
- I gathered that much of the unit's active equipment was either replaced or sent to the vendor for refurbishment.

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

How many nuclear plants does it take to meet the world's energy needs?

Several weeks ago Joshua Pearce at Clarion University in Pennsylvania released a study titled “ Thermodynamic limitations to nuclear energy deployment as a greenhouse gas mitigation technology .” In the study he stated... nuclear energy production would have to increase by 10.5% per year from 2010 to 2050 to both replace fossil-fuel-energy use and meet the future energy demands. This line, of course, made the headlines and has been picked up by several outlets and blogs . When looking into his calculations for this statement, he made one assumption error that overstated the above sentence by nearly a factor of three. Page 121, Section 4.1 of the study states: Richard Smalley pointed out that in 2004, the global economy consumed the equivalent of 220 million barrels of oil per day, which converted into electricity terms is the equivalent of 14.5 TeraWatts (TW), or 14,500,000 MegaWatts (MW) (2005). … With a nuclear plant having about 1000 MW (1 GW) of capacity, we would need 14,500...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...