From NEI’s Japan micro-site

Robot Tests Radiation in Fukushima Reactor Building

Plant Status

  • Work is continuing to reduce radiation levels at Fukushima Daiichi’s reactor 3 building. Tokyo Electric Power Co. has used robots to vacuum radioactive debris and place steel sheets on the floor to decrease the potential for radiation exposure. Pending a reduction in radiation levels,  workers are scheduled to enter the building housing the reactor on July 17 to begin installing new piping to inject nitrogen gas into the reactor containment vessel. The inert gas will reduce the possibility of a hydrogen explosion in the containment building. The company already is injecting nitrogen into the containments for reactors 1 and 2.
  • TEPCO said debris may have clogged a hose, temporarily reducing the flow of cooling water into reactor 1 at Fukushima Daiichi by about one-quarter of normal volume. Normally, the cooling system injects 3.7 metric tons of water an hour into the reactors, but the flow was reduced Monday to about 3 metric tons per hour, setting off an alarm. Workers began injecting more water, restoring normal flow in less than an hour.

Industry/Regulatory/Political Issues

  • The Japanese government is taking over the radiation surveys being conducted by local governments and TEPCO in the area around Fukushima Daiichi. Schools and other areas where children gather will have priority.
  • The mayor of a town in the southwestern Japan prefecture of Saga said he agrees with restarting a nuclear energy facility there. Other prefecture officials must also sign off on restarting electricity production at two reactors at Kyushu Electric Power Co.’s Genkai plant. Thirty-five reactors, representing two-thirds of the country’s nuclear energy capacity, remain shut down because of the effects of the March earthquake and tsunami or for regular inspections.
  • A research ship is collecting samples from the ocean floor near Fukushima prefecture to test for radiation. The research is focusing on shellfish and sandworms.

Media Highlights

  • A New York Times writer toured the LaSalle nuclear energy facility in Illinois and reports on how the plant—and the industry—handles used nuclear fuel.

New Products

  • NEI’s new Safety First website provides information about nuclear safety, security and measures to protect public health.

Upcoming Events

  • The task force reviewing NRC processes and regulations in light of the accident at Fukushima Daiichi will brief the commissioners on the report at a public meeting on July 19. The briefing will be webcast.

Comments

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...

How Much Land Does Nuclear, Wind and Solar Really Need?

Not too long ago, we reviewed a report that looked at nuclear energy (and other energy sources) as biodiversity agents. This had to do, in part, with the amount of land a facility needs to function. Nuclear energy and fossil fuel plants use relatively little, wind farms and solar arrays quite a lot of land . Based on an objective and transparent analysis of our sustainable energy choices, we have come to the evidence-based conclusion that nuclear energy is a good option for biodiversity conservation (and society in general) and that other alternatives to fossil fuels should be subjected to the same cost–benefit analyses (in terms of biodiversity and climate outcomes, as well as sociopolitical imperatives) before accepting or dismissing them. Writer Barry Brook, who collected 75 scientists to endorse his paper, is interested in land use as it impacts flora and fauna. Biodiversity concerns do not get as much play as they might – and, when they do, it annoys many when land is withdraw...