Thoughts on the DOE Loan Guarantee Program

The Department of Energy is moving forward with its clean energy Loan Guarantee program. In a press release last week, DOE announced that it had received applications from 17 companies to build 14 nuclear power plants totaling 21 new units and almost 29,000 megawatts of new electrical capacity. In total, the applications seek $122 billion in loan guarantees, while the program is authorized to commit only $18.5 billion to new nuclear plants. Following the DOE announcement, NEI's Richard Myers, Vice President, Policy Development, noted in an interview with Bloomberg that the oversubscription is a sign that $18.5 billion is not adequate to provide the financing support necessary. In a piece on the loan guarantee program and another on the debt ceiling of the Tenessee Valley Authority, Dan Yurman explains why.

In essence, there are some jobs so big they are beyond what the private sector alone can do. Federal support, such as loan guarantees, enables the private sector to attract more capital to the enormous projects needed than would occur otherwise. Without that public-private partnership, the entire cost of these massive projects would be borne entirely by the federal government (i.e., the taxpayers). With federal encouragement, the private sector is willing to bear a fair share of the risk and put its money on the line to contribute to dealing with the nation's energy and environmental needs. That's what we take from the oversubscription in loan guarantee applications last week.

Comments

Anonymous said…
Looks like these plants average 7.1 billion each. Would the total cost of the plant be guaranteed or is there more cost than this?
David Bradish said…
Martin, in order to receive a loan guarantee, as much but not more than 80% of the project costs can be financed by debt. The loan guarantee backs all of the debt. The other 20% has to come from equity.

So if the plant costs $7.1B, then the government can guarantee at most up to 80% of the total cost (depending on how the utility wants to finance the project) or $5.7B.
Arvid said…
Of course, one idea is that the government does carry 100 % of the cost, and ownership, like in France...

By the way, does the industry pay anything for these loan guarantees? One could argue that they won't cost the US government a single cent as long as nothing goes wrong, but the government is taking on quite a bit of risk which could end up as real debts. And the guarantees are obviously very valuable to the industry, one could probable even put a dollar value on them.

I propose a bold and (imho) fair plan: give loan guarantees to all serious power projects in the US! That would be fair but would tilt the competitive board so capital intensive technologies (wind and nuclear) become more competitive than they are today.

Of course, you could argue that it wouldn't tilt anything, and that the current system instead is tilted in the interest of low capital plants, that is, gas.

As a matter of fact, that is exactly what I claim: in the power business there is no such thing as a level playing field, just a number of diifferently sloping ones, and it's up to the government to choose the one which is most in the national interest.
David Bradish said…
By the way, does the industry pay anything for these loan guarantees?

Definitely. Here's what Exelon will pay for the loan guarantee on the two proposed reactors in Texas:

"Exelon will pay DOE a program fee of more than $400 million for the application, Nesbit said. There will also be an annual loan maintenance fee of $200,000 to $400,000, a one-time facility fee of about $55 million and a one-time application fee of about $800,000."

One could argue that they won't cost the US government a single cent as long as nothing goes wrong

We try to make that argument, but it doesn't always get heard. Oh well, gotta keep at it.

Popular posts from this blog

Fluor Invests in NuScale

You know, it’s kind of sad that no one is willing to invest in nuclear energy anymore. Wait, what? NuScale Power celebrated the news of its company-saving $30 million investment from Fluor Corp. Thursday morning with a press conference in Washington, D.C. Fluor is a design, engineering and construction company involved with some 20 plants in the 70s and 80s, but it has not held interest in a nuclear energy company until now. Fluor, which has deep roots in the nuclear industry, is betting big on small-scale nuclear energy with its NuScale investment. "It's become a serious contender in the last decade or so," John Hopkins, [Fluor’s group president in charge of new ventures], said. And that brings us to NuScale, which had run into some dark days – maybe not as dark as, say, Solyndra, but dire enough : Earlier this year, the Securities Exchange Commission filed an action against NuScale's lead investor, The Michael Kenwood Group. The firm "misap

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Wednesday Update

From NEI’s Japan micro-site: NRC, Industry Concur on Many Post-Fukushima Actions Industry/Regulatory/Political Issues • There is a “great deal of alignment” between the U.S. Nuclear Regulatory Commission and the industry on initial steps to take at America’s nuclear energy facilities in response to the nuclear accident in Japan, Charles Pardee, the chief operating officer of Exelon Generation Co., said at an agency briefing today. The briefing gave stakeholders an opportunity to discuss staff recommendations for near-term actions the agency may take at U.S. facilities. PowerPoint slides from the meeting are on the NRC website. • The International Atomic Energy Agency board has approved a plan that calls for inspectors to evaluate reactor safety at nuclear energy facilities every three years. Governments may opt out of having their country’s facilities inspected. Also approved were plans to maintain a rapid response team of experts ready to assist facility operators recoverin