NRC Issues Press Release Concerning North Anna Re-Start

The following press release was just issued by NRC.
NRC CONFIRMS POST-EARTHQUAKE REQUIREMENTS FOR
THE NORTH ANNA NUCLEAR POWER PLANT

The Nuclear Regulatory Commission has informed Dominion Generation, operator of the two-reactor North Anna nuclear power plant near Louisa, Va., of actions that must be completed before the agency will authorize the restart of the plant. The plant shut down safely following the Aug. 23 earthquake near Louisa.

“We’re reviewing Dominion’s information to ensure North Anna’s systems will be able to keep the public safe and the plant won’t start up again until we’re satisfied on that point,” said Eric Leeds, director of the NRC’s Office of Nuclear Reactor Regulation. “We’re working diligently on coming to a technically sound decision.”

The NRC has issued Dominion a Confirmatory Action Letter, which reiterates that since the Aug. 23 earthquake exceeded design parameters for North Anna, the plant will remain shut down until Dominion demonstrates “to the Commission that no functional damage occurred to those features necessary for continued operation without undue risk to the health and safety of the public.” The letter then lays out the next steps in the restart process, starting with Dominion submitting documentation responding to all NRC questions regarding restart safety.

“Inspectors from the NRC Region II office and other agency experts will conduct additional onsite inspections at North Anna to verify that adequate actions have been taken in response to the Confirmatory Action Letter,” said Victor McCree, administrator of the NRC’s Atlanta office.

The NRC will also complete a safety evaluation regarding restart. The NRC’s directive will remain in effect until the NRC is satisfied Dominion has demonstrated the plant is safe to operate; at that point the agency would issue written permission for Dominion to restart the plant. North Anna Unit 2 is currently in a refueling outage and is shut down for refueling and associated maintenance.

###
More details as we get them.

Comments

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

How many nuclear plants does it take to meet the world's energy needs?

Several weeks ago Joshua Pearce at Clarion University in Pennsylvania released a study titled “ Thermodynamic limitations to nuclear energy deployment as a greenhouse gas mitigation technology .” In the study he stated... nuclear energy production would have to increase by 10.5% per year from 2010 to 2050 to both replace fossil-fuel-energy use and meet the future energy demands. This line, of course, made the headlines and has been picked up by several outlets and blogs . When looking into his calculations for this statement, he made one assumption error that overstated the above sentence by nearly a factor of three. Page 121, Section 4.1 of the study states: Richard Smalley pointed out that in 2004, the global economy consumed the equivalent of 220 million barrels of oil per day, which converted into electricity terms is the equivalent of 14.5 TeraWatts (TW), or 14,500,000 MegaWatts (MW) (2005). … With a nuclear plant having about 1000 MW (1 GW) of capacity, we would need 14,500...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...