Guest Post: Nuclear Energy and the Value of CWIP


Bottom of containment vessel for new reactor at Plant Vogtle
The following guest post was written by NEI's Mitch Singer.

Jeff McMahon bases his argument against nuclear cost recovery “Editors Rebel Against Ratepayer Financing For Nuclear Plants,” on the sole premise that because natural gas is inexpensive at this point in time it will remain so for decades. Therefore, energy companies should rely solely on one source of electricity generation. Ignoring the old adage of not putting your eggs in one basket is as relevant in generation choices as it is in financial investments.

Energy companies evaluate a variety of factors to determine their generating mix and plan not in years, but rather decades ahead. Public utility commissioners do the same. They conduct an extensive analysis of the state’s demand growth commonly known as a “determination of needs” that looks at all methods of generation to see which ones are most suitable. Commissioners are also obligated to make sure there is diversification in the state’s generating portfolio, balance economic and environmental concerns and try to keep costs down.

Florida, for example, receives 62 percent of its electricity from natural gas and an overall 86 percent from fossil fuels. Natural gas may be low now, but history has proven on many occasions that low natural gas prices in the U.S. are not sustainable. Within the last month we’ve seen the price of natural gas spike to more than $30 per million BTU on the spot market in New England due to frigid weather and a shortage of natural gas pipeline capacity. So what did New England do to mitigate the impact? It imported significant amounts of electricity from the Indian Point nuclear plant in New York.

Here in lies the value of nuclear energy as it provides a stable, low-operating cost baseload source of electricity that offers a myriad of economic and environmental benefits. Nuclear cost recovery, commonly known as construction work in progress (CWIP), allows a utility to recover financing costs and return on equity. By doing so, a utility avoids paying “interest on interest” that would occur if all costs are held until the plant goes into service. 

In Georgia, where Southern Co. and Georgia Power are building two new reactors at Plant Vogtle, just this past week the Georgia Public Service Commission (PSC) approved the latest cost and schedule reports. One PSC staff member put the reasoning succinctly, saying the projectremains more economically viable than any other (fuel) resource, including a natural gas-fired alternative.”


In Georgia, CWIP is expected to save Southern Company’s ratepayers $300 million in financing costs during construction. CWIP also will reduce the in-service cost of the plant by $2 billion, saving customers additional financing costs over its expected 60-year life. The utility also has improved cash flows through CWIP that support stronger financial ratings, which result in lower interest costs for the project and all other utility investments over the long term. CWIP is allowed by public utilities and the Federal Energy Regulatory Commission to support the construction of baseload electricity plants and transmission lines for a simple reason: because it saves money for consumers and gets necessary infrastructure constructed.

New nuclear power plants also act as a macro-economic catalyst. The reliable, low-cost electricity provided by nuclear plants operates at close to 90 percent capacity. Thus, nuclear’s forward price and supply stability provide a high level of confidence in attracting capital formation to start new businesses and expand existing businesses, which results in job formation and expanded tax revenues. The Plant Vogtle project is about one-third completed and has already generated almost 5,000 jobs during the construction period and there will be about 700 permanent, high-paying jobs associated with the two new reactors when they’re completed by the end of this decade. In addition the average nuclear plant generates approximately $470 million a year in total output for the local community and about $40 million per year in total labor income. Nuclear also bring the environmental benefit of being the largest source of emission-free electricity.

Natural gas may be the preferred generation choice of today. But as Roman conquerors were warned during the celebrations of their triumphs; all glory is fleeting.

Comments

Nuclear power is carbon neutral while producing electricity from natural gas increases climate change, global sea level rise, and the acidification of the oceans.

Natural gas is the future of electricity production in the US, only if we intend to severely damage our environment for future generations.


Marcel F. Williams
Anonymous said…
Don't forget that fugitive emissions of methane from the natural gas extraction step alone dwarf the carbon footprint from the entire nuclear lifecycle. Methane produces atmospheric damage in about a 70:1 ratio with CO2. Anyone who advocates any kind of energy system that increases the use of natural gas (e.g., windpower, since gas turbines need to be available for quick-start backup power) is no friend of the environment.
Anonymous said…
Are the utility companies also allowed to charge CWIP to pay for construction of natural gas fired units? I only ever hear about CWIP in relation to nuclear construction / upgrades.
Anonymous said…
The reason you hear about AFUDC and CWIP around nuclear plants so much is because the amount of capital is much larger and the timeline is much longer. For a natural gas plant the capitalized interest and financing costs are a much lower percentage of the total cost of the power produced by the plant and therefore it isn't really a big deal how the financing is done.
Anonymous said…
Well, I understand that the interest is lower on gas-fired plants because they (1) cost less and (2) are built quicker. But the objections to CWIP are often philosophical ("why should I pay for a plant before I get the power?") so, I am still curious if CWIP is applied to the gas-fired plants.
Steve Aplin said…
excellent post, and I totally agree: allowing utilities to finance projects via CWIP-based rates is THE BEST way to get zero-carbon capacity working as quickly as possible. Ontario has done that creatively, in the case of Bruce Power -- see http://canadianenergyissues.com/2013/04/04/how-to-create-infrastructure-jobs-and-pay-for-clean-energy-public-and-private-models-deliver-success-in-ontario/

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

How many nuclear plants does it take to meet the world's energy needs?

Several weeks ago Joshua Pearce at Clarion University in Pennsylvania released a study titled “ Thermodynamic limitations to nuclear energy deployment as a greenhouse gas mitigation technology .” In the study he stated... nuclear energy production would have to increase by 10.5% per year from 2010 to 2050 to both replace fossil-fuel-energy use and meet the future energy demands. This line, of course, made the headlines and has been picked up by several outlets and blogs . When looking into his calculations for this statement, he made one assumption error that overstated the above sentence by nearly a factor of three. Page 121, Section 4.1 of the study states: Richard Smalley pointed out that in 2004, the global economy consumed the equivalent of 220 million barrels of oil per day, which converted into electricity terms is the equivalent of 14.5 TeraWatts (TW), or 14,500,000 MegaWatts (MW) (2005). … With a nuclear plant having about 1000 MW (1 GW) of capacity, we would need 14,500...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...