Not too long ago, we reviewed a report that looked at nuclear energy (and other energy sources) as biodiversity agents. This had to do, in part, with the amount of land a facility needs to function. Nuclear energy and fossil fuel plants use relatively little, wind farms and solar arrays quite a lot of land . Based on an objective and transparent analysis of our sustainable energy choices, we have come to the evidence-based conclusion that nuclear energy is a good option for biodiversity conservation (and society in general) and that other alternatives to fossil fuels should be subjected to the same cost–benefit analyses (in terms of biodiversity and climate outcomes, as well as sociopolitical imperatives) before accepting or dismissing them. Writer Barry Brook, who collected 75 scientists to endorse his paper, is interested in land use as it impacts flora and fauna. Biodiversity concerns do not get as much play as they might – and, when they do, it annoys many when land is withdraw...
Comments
http://www.rmi.org/images/PDFs/Energy/E08-01_AmbioNucIllusion.pdf
Since the Keystone findings, new nuclear plants’ uniquely rapid capital-cost escalation,
far from abating, has accelerated. The same top trade journal summarizes how the latest analyses,
including one by Keystone coauthor Jim Harding (former director of strategic planning at
Seattle City Light), have found the Keystone report’s lower cost range of $3,600/kW “no longer
believable” and its upper range of $4,000/kW “probably low.”27 Harding’s estimate of total current
construction costs (2007 $ including interest during construction) of ~$4,300–4,550/kW
matches prospective customer Constellation’s published, then redacted, estimate of
~$4,300/kW.28 That’s slightly above Standard & Poor’s (S&P’s) May 200729 and American Electric
Power’s August 2007 estimates of ~$4,000/kW, but well below Moody’s October 2007 estimate30
of ~$5,000–6,000/kW—which Moody’s called admittedly “only marginally better than a
guess” but still solid grounds for caution.
By early 2008, industry estimates were creeping even above Moody’s dismaying range.
In September 2007, Lew Hay, CEO of FPL Group, said the total cost of a new nuclear plant (all
in mixed future dollars as-spent) could be ~$5,000–7,000/kW, or “on the order of magnitude of
$13 to $14 billion” for a two-unit plant. Yet just five months later, FPL31 filed formal cost estimates
up to nearly twice that high—$12–24 billion (again in mixed future dollars) for a 2.2–
3.04-GW two-unit plant, equivalent to ~$4,200–6,100/kW in 2007.
AmbioNucIllusion.pdf
Try again :>)
Anon, no doubt nuclear plants are expensive to build. Many utilities, however, have found that all electricity technologies have become substantially more expensive as well and that new nuclear plants are still economical.
I'm doing research for a paper. Could someone tell me whether these plants are the earliest new plants to come on line in the U.S.? How about worldwide?
Is there an official report on this somewhere.
thanks,
Here's a link for online dates of U.S. plants and here's a link for the same dates for world plants.