Another Non-proliferation Success Story

On May 5, Eric posted a note on "Megatons to Megawatts". I would like to call attention to an excellent project that complements "Megatons to Megawatts". It's the MOX Project. Whereas "Megatons to Megawatts" converts surplus weapons-grade uranium to fuel, the MOX Project converts surplus weapons-grade plutonium. It's a bilateral project, with both Russia and the U.S. having agreed to convert 34000 kg of weapons-grade plutonium into fuel.

Like most major projects, the MOX Project has encountered and overcome various obstacles. One of the most notable obstacles was that there is no facility in the U.S. that is licensed to fabricate MOX fuel. So that the project could continue to make progress until such a facility becomes available, plutonium dioxide was shipped to Cadarache in France, where it was mixed with uranium dioxide and formed into fuel pellets. The pellets, plus cladding and hardware from the U.S., were then sent to the Mélox facility, also in France, for assembly into (what else?) fuel assemblies. The assemblies were subsequently returned to the U.S.

MOX fuel has been used safely in over 30 European reactors. Where the MOX Project breaks new ground is in the details of the fuel isotopics. European MOX uses reactor-grade plutonium, which is recycled from used commercial reactor fuel. The MOX Project is using weapons-grade plutonium, which, like the uranium for "Megatons to Megawatts", is derived from actual weapons.

As I write this, Duke's Catawba 1 reactor is shut down for a historic refueling in which four MOX lead assemblies will be placed in the core. It is the first use of weapons-grade MOX in a commercial power reactor. Irradiation will destroy most of plutonium, and it will degrade the isotopics of the remaining plutonium so that it is no longer militarily useful. It's another non-proliferation success story.

Technorati tags: , , , , ,

Comments

Kelly L Taylor said…
So, Kevin, that means that if there were a operational reprocessing facility in the US, the materials that comprise mixed oxide fuel wouldn't need so many passport stamps and global mileage before making electricity? Sounds like an intriguing prospect for future energy independence and related national security, to me!

It's great to see you blogging here! I look forward to more of your contributions.
Anonymous said…
I appreciate Kevin McCoy's posting. In fact, by testifying as an expert witness in the Atomic Safety and Licensing Board hearing last summer, Kevin played a key role in obtaining the regulatory approval for using the four MOX fuel lead assemblies at Catawba.

As a caution, note that it took the Nuclear Regulatory Commission's Atomic Safety and Licensing Board more than 18 months to conclude that using four MOX fuel lead test assemblies at one nuclear power plant is OK. This despite the fact that dozens of MOX assemblies are routinely loaded into dozens of nuclear power plants in European countries. The opportunity for intervenors to cause mischief and unnecessary delay is far too high. I doubt seriously that we are going to achieve a "nuclear renaissance" until we drastically reform the regulatory process in this country.

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

How many nuclear plants does it take to meet the world's energy needs?

Several weeks ago Joshua Pearce at Clarion University in Pennsylvania released a study titled “ Thermodynamic limitations to nuclear energy deployment as a greenhouse gas mitigation technology .” In the study he stated... nuclear energy production would have to increase by 10.5% per year from 2010 to 2050 to both replace fossil-fuel-energy use and meet the future energy demands. This line, of course, made the headlines and has been picked up by several outlets and blogs . When looking into his calculations for this statement, he made one assumption error that overstated the above sentence by nearly a factor of three. Page 121, Section 4.1 of the study states: Richard Smalley pointed out that in 2004, the global economy consumed the equivalent of 220 million barrels of oil per day, which converted into electricity terms is the equivalent of 14.5 TeraWatts (TW), or 14,500,000 MegaWatts (MW) (2005). … With a nuclear plant having about 1000 MW (1 GW) of capacity, we would need 14,500...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...