INPO Compiles Timeline of Fukushima Events After Japan Earthquake, Tsunami

Just a few minutes ago, the Institute of Nuclear Power Operations published a detailed timeline of events at the Fukushima Daiichi nuclear power station following the March 11 earthquake and tsunammi (click here for the PDF of the report). The full text of the Nuclear Energy Institute news release announcing the publication follows below:
INPO Compiles Timeline of Fukushima Events After
Japan Earthquake, Tsunami

4-Day Chronology Provides Common Baseline of Facts To
Inform Response Activities by U.S. Industry, Government

WASHINGTON, D.C., Nov. 11, 2011—The Institute of Nuclear Power Operations has compiled a detailed timeline of events at the Fukushima Daiichi nuclear power station after the March 11 earthquake and tsunami in Japan. The detailed report, prepared as part of the integrated response to the Japan events, was delivered today to U.S. industry executives, the Nuclear Regulatory Commission and to members of Congress.

“The U.S. nuclear energy industry is committed to learning from Japan’s experience and applying relevant lessons to make U.S. nuclear energy facilities even safer. We are sharing this report with the widest possible audience because it is important that we all work from the same set of facts in determining the appropriate response,” said NEI’s senior vice president and chief nuclear officer, Tony Pietrangelo. “It is of paramount importance that we learn from it and take our facilities to even higher levels of safety and preparedness.”

U.S. nuclear power plants operating in 31 states produce 20 percent of U.S. electricity, with a unique combination of 24/7 production, industry-leading reliability and zero carbon emissions or air pollution.

The report presents a chronology of activities at the Fukushima Daiichi station in the first four days after the earthquake and tsunami. It does not provide analysis, draw conclusions or include recommendations on the events. Most of the information in the report has been previously released, but in a piecemeal fashion. The Institute of Nuclear Power Operations, an industry organization whose mission is to promote the highest levels of safety throughout the U.S. nuclear industry, worked closely with the Tokyo Electric Power Co., the plant’s operator, to develop the timeline. Information was compiled from multiple sources, including the Japanese government, the International Atomic Energy Agency, and several Japanese nuclear and safety organizations.

The U.S. nuclear energy industry has established a leadership model among major electric sector organizations – including NEI, the Electric Power Research Institute, reactor vendors and INPO – to integrate and coordinate the nuclear industry’s ongoing response to the Fukushima Daiichi accident.

This Fukushima Response Steering Committee already has identified five areas that warrant action or further examination:

  • Seismic and flooding inspections
  • Maintaining safety during a prolonged loss of AC power
  • Assuring the accessibility and functionality of reactor containment vent valves assuming loss of AC power
  • Enhanced training in guidelines to manage severe accidents
  • Enhanced monitoring of used fuel storage pools at reactors

  • “This timeline doesn’t tell us why events unfolded – a comprehensive root cause analysis will likely take several months if not years to achieve that understanding. However, the facts presented in this timeline reinforce the industry’s and the NRC’s independent assessments on what our response priorities should be,” Pietrangelo said.

    The timeline is available here and at NEI’s “Safety First” website, http://safetyfirst.nei.org.
    More to come.

    Comments

    Popular posts from this blog

    Activists' Claims Distort Facts about Advanced Reactor Design

    Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

    How many nuclear plants does it take to meet the world's energy needs?

    Several weeks ago Joshua Pearce at Clarion University in Pennsylvania released a study titled “ Thermodynamic limitations to nuclear energy deployment as a greenhouse gas mitigation technology .” In the study he stated... nuclear energy production would have to increase by 10.5% per year from 2010 to 2050 to both replace fossil-fuel-energy use and meet the future energy demands. This line, of course, made the headlines and has been picked up by several outlets and blogs . When looking into his calculations for this statement, he made one assumption error that overstated the above sentence by nearly a factor of three. Page 121, Section 4.1 of the study states: Richard Smalley pointed out that in 2004, the global economy consumed the equivalent of 220 million barrels of oil per day, which converted into electricity terms is the equivalent of 14.5 TeraWatts (TW), or 14,500,000 MegaWatts (MW) (2005). … With a nuclear plant having about 1000 MW (1 GW) of capacity, we would need 14,500...

    What Happens During a Refueling Outage?

    You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...