NRC Moves Forward on Exelon ESP Application

Last week, the NRC announced its preliminary conclusion that they have found no environmental impacts that would prevent approval of Exelon’s Early Site Permit (ESP) application for the Clinton plant in Illinois. This article appeared in the St. Louis Post-Dispatch last week.

The article highlights an important point:
Besides environmental effects, the commission also is considering site safety and emergency planning. The commission has said it wants to make a decision on Exelon's application by August next year.
The myriad of other issues associated with licensing a new nuclear plant are addressed during other steps of the process like the certification of plant design and the application for a combined construction and operating license.

This is a concept that, in my experience, many antinuclear extremists can’t seem to grasp. They will allege that an ESP application is incomplete because it doesn’t say enough about specific safety features of the plant design or it doesn’t address storage or disposal of spent fuel.

Occasionally, when this feature of the licensing process is pointed out, a better-versed antinuclear leader will say, “Yes, and that is a fundamental flaw in the regulations. All of these issues should be addressed together.” I find this logic ludicrous. How does one provide sufficiently detailed analyses of safety systems when a design hasn’t been chosen? And how can one provide specifics of spent fuel storage and disposal when the parameters of the fuel are not yet known? Any such analyses at the ESP stage would be speculative at best and would not serve well the interests of the NRC, the utility, or the public.

Comments

Norris McDonald said…
Great new about Exelon. Now if they could get new plant on line in seven years I would really be impressed. Does Exelon really understand how important speed is here? And this assumes that they have excellent quality control.
Lisa Stiles said…
I think that all the utilities that are pursuing ESPs are aware of the importance of showing investors that plants can be built on schedule.

I'm not in a position to know exact timeframes but the information I've gleaned at conferences and the like is that utilities and vendors would want to be sure they can have a new plant on line 4 years from the time the order is placed.

Of course, orders won't be placed until and if licensing and economic issues are resolved favorably. Given the length of time for the different steps in the licensing process, I doubt seriously that we will see a new nuclear plant online by the 2010 DOE target. But if everything comes together, I don't think it is unrealistic to expect a new one before 2015.

Popular posts from this blog

Activists' Claims Distort Facts about Advanced Reactor Design

Below is from our rapid response team . Yesterday, regional anti-nuclear organizations asked federal nuclear energy regulators to launch an investigation into what it claims are “newly identified flaws” in Westinghouse’s advanced reactor design, the AP1000. During a teleconference releasing a report on the subject, participants urged the Nuclear Regulatory Commission to suspend license reviews of proposed AP1000 reactors. In its news release, even the groups making these allegations provide conflicting information on its findings. In one instance, the groups cite “dozens of corrosion holes” at reactor vessels and in another says that eight holes have been documented. In all cases, there is another containment mechanism that would provide a barrier to radiation release. Below, we examine why these claims are unwarranted and why the AP1000 design certification process should continue as designated by the NRC. Myth: In the AP1000 reactor design, the gap between the shield bu...

What Happens During a Refueling Outage?

You may have noticed over the past few weeks that a number of nuclear plants are shut down for refueling outages or are resuming operations after just returning from one. This type of routine outage usually occurs in the spring or fall when electricity demand is low so that nuclear reactors can replace about one-third of the spent fuel rods with new fuel and conduct other routine maintenance and repairs at the plant. To get a better sense of how refueling works at a nuclear energy facility, I spoke with Marcus Nichol, NEI’s senior project manager for used fuel storage and transportation, and asked him to explain the basics. Why does a nuclear plant need to replace one-third of its fuel? Nichol: The main purpose of a refueling outage is to replace older fuel that is depleted—meaning it can no longer efficiently produce energy from nuclear fission reactions—with new fuel. This “used fuel” has typically been used in the reactor for four-and-a-half to six years before it is pe...

How Much Land Does Nuclear, Wind and Solar Really Need?

Not too long ago, we reviewed a report that looked at nuclear energy (and other energy sources) as biodiversity agents. This had to do, in part, with the amount of land a facility needs to function. Nuclear energy and fossil fuel plants use relatively little, wind farms and solar arrays quite a lot of land . Based on an objective and transparent analysis of our sustainable energy choices, we have come to the evidence-based conclusion that nuclear energy is a good option for biodiversity conservation (and society in general) and that other alternatives to fossil fuels should be subjected to the same cost–benefit analyses (in terms of biodiversity and climate outcomes, as well as sociopolitical imperatives) before accepting or dismissing them. Writer Barry Brook, who collected 75 scientists to endorse his paper, is interested in land use as it impacts flora and fauna. Biodiversity concerns do not get as much play as they might – and, when they do, it annoys many when land is withdraw...